November 3, 2026

Kitchen remodeling in Aurora, CO goes smoothly when the work happens in the right order. Planning comes first, then ordering, then demolition and rough-in, then cabinets, countertops, and finishes. AXXESS Painting and Remodeling, based in Thornton, Colorado, serves the Aurora area, and the questions we hear most are about sequence: what happens first, what waits on what, and what it means for daily life at home.
This guide walks through that sequence for a typical kitchen. It also covers what Aurora's own permit handbook says about when a permit is needed, how to cook while the kitchen is torn up, and how to compare bids. We do not quote prices here, because costs depend on the scope, the materials, and the home.
For a broader look at planning choices and budgets, see our kitchen remodeling planning guide for Broomfield. This post is about timing and order of work, not layout or budget.
A kitchen remodel follows four phases: planning, ordering and preparation, demolition and rough-in, then installation and finishing. Each phase depends on the one before it. Cabinets cannot be installed until walls, plumbing, and wiring are ready, and countertops cannot be measured until the cabinets are in place.
KraftMaid, a cabinet manufacturer, publishes the same four-phase outline on its remodeling steps page. Here is how each phase looks in practice.
Planning is where you set goals, measure the room, collect samples, and get written proposals. It has no fixed length. KraftMaid describes the time frame as "as long as you need," and we agree. A rushed plan creates change orders later, and change orders cost time.
This is where you order cabinets, fixtures, flooring, and appliances. It is also when you box up dishes and set up a temporary kitchen. The long wait is usually cabinets. KraftMaid states that its cabinets take a minimum of 4 weeks to arrive. Other makers and custom shops may differ, so ask for the lead time in writing.
Demolition removes old cabinets, counters, and flooring as the plan requires. Rough-in is the plumbing, electrical, and heating or cooling work that happens inside the walls and floors before they are closed up. Drywall repair and painting follow. KraftMaid lists this phase at a few days to two weeks.
Cabinets arrive and get inspected for shipping damage. Flooring goes in, then cabinets, then countertops are measured and installed. Lighting, faucets, backsplash, hardware, and finish carpentry come last. KraftMaid lists this phase at 4 to 6 weeks.
Most kitchen remodels take several weeks to a few months from the first demolition day to final cleanup, depending on size and scope. KraftMaid says a project "may last a few weeks or a few months." The biggest swing factors are cabinet delivery, permit review, and how quickly the household makes decisions.
Here is what moves the calendar the most:
The practical takeaway: the schedule your contractor gives you is only as good as your decisions made before demolition. Finish the design, order the long-lead items, and confirm delivery dates before you remove a single cabinet.
Often yes, if the work changes plumbing, wiring, or walls. Aurora's DIY and DIR brochure says that changing anything within the wall space, such as wiring or plumbing, needs a building permit. Replacing cabinets, countertops, sinks, and appliances usually does not, but moving a sink does.
The same city brochure lists a few more points that matter for kitchens:
That handbook is dated March 2019 and itself says requirements may change. Before you plan around any of this, call or visit the Aurora Building Division and confirm current rules for your exact scope. We do not give permit advice for your address, and neither should anyone who has not seen your plan.
Permit rules also differ from one city to the next. If you are comparing, our Boulder kitchen remodeling post on permits and layout covers a different city's process.
Set up a temporary kitchen in another room before demolition starts. A folding table, a microwave, a small cooler or spare refrigerator, a toaster oven, and paper or reusable dishes cover most households. Plan simple meals and keep a sink alternative, such as a bathroom or utility sink, for washing up.
KraftMaid's own timeline puts "box up dishes and set up a temporary kitchen" in the ordering and preparation phase. We agree with that placement. Doing it early means demolition day is not also moving day.
Dust travels. Ask your contractor how they plan to contain it, for example with plastic barriers and floor protection from the work area to the exit. Agree on a daily cleanup routine and where tools and materials will stay. Pets, kids, and work crews all share the same floor, so a clear path helps everyone.
Decide the layout, cabinet style and size, countertop material, appliance models, sink and faucet, lighting plan, and flooring before demolition. These choices set plumbing, wiring, and measurements. Changing them after walls are open usually costs time and money, and it can reset inspections.
A short pre-demolition checklist keeps everyone aligned:
It can. Older homes more often hide outdated wiring, plumbing, or finishes inside the walls, and homes built before 1978 may involve lead-based paint. If paint will be disturbed in a pre-1978 home, EPA's Renovation, Repair and Painting rule applies to paid work, and the firm doing it must be certified.
EPA states the rule covers houses, apartments, and child-occupied facilities built before 1978. It says anyone paid to perform work that disturbs paint in those buildings must be certified, including all firms, even sole proprietorships. Ask any contractor you interview about this before you sign.
Beyond lead, here is what older kitchens commonly bring to the plan:
Refresh when the layout works and the cabinet boxes are sound. Remodel when the layout, storage, or appliances no longer fit how you cook. A refresh can mean painted or refaced cabinets, new hardware, a new backsplash, and updated lighting. A full remodel changes the room itself.
Use this quick comparison to see which path fits your goals:
Compare bids line by line, not by total. Ask each contractor for a written scope, material list, timeline, and permit plan. A lower number that leaves out demolition cleanup, drywall repair, or painting can cost more once those items are added back in.
Questions that help you compare:
AXXESS Painting and Remodeling is licensed and fully insured, and uses premium materials and techniques. Our kitchen remodeling process starts with a free consultation at your home, followed by a detailed written proposal covering scope, material options, timeline, and costs. After you approve it, we help you choose countertops, cabinets, tile, and fixtures. The crew then handles demolition, construction, installation, and finishing, and the project ends with a final walkthrough where you review every detail and we make any needed adjustments.
Our kitchen work covers cabinet installation, replacement, or refacing, countertop installation, backsplash tile, flooring, sink and fixture upgrades, lighting updates, plumbing and electrical coordination, drywall repair and painting, and trim and finish carpentry. You can read the full list on our kitchen remodeling page. We are based in Thornton and serve the Aurora area.
Order as soon as the layout is final and before demolition starts. KraftMaid says its cabinets take a minimum of 4 weeks to arrive, and other makers vary. Get the delivery estimate in writing so your demolition date matches the real arrival date.
Not for a full remodel. Once demolition begins, the sink, range, and refrigerator are usually out of service for some portion of the project. Set up a temporary kitchen first, and ask your contractor when each appliance and the water will be off.
Aurora's DIY and DIR brochure says replacing cabinets, countertops, sinks, toilets, and appliances usually does not need a permit, while moving a sink or changing anything inside the walls does. Rules can change, so confirm with the Aurora Building Division before you start.
If a permit is required, inspections follow. The city says required inspections include a rough inspection and a final inspection. Ask your contractor in advance who schedules them, and make sure the work is accessible when the inspector arrives.
KraftMaid's outline places drywall and painting in the demolition and rough-in phase, before cabinets are installed. Finish carpentry and fixtures come later, so many crews plan a final touch-up pass. Ask your contractor how they sequence painting on your project.
A good kitchen remodel starts with a clear order of work and honest timing. If you are thinking about kitchen remodeling in the Aurora area, AXXESS Painting and Remodeling can walk through your goals, scope, and schedule at a free estimate. Call (720) 226-5092, email axxessp.r1@gmail.com, or request your free estimate online. You can also learn more about our team or see our general residential construction services.